Project Description

Client: Meggitt Aircraft Braking Systems

Project Duration: Phase 1 18 weeks, Phase 2 30 weeks

Project Scope:

Asbestos Removal and demolition of numerous buildings on the Aircraft Braking Plant in Coventry.

Project Constraints & Challenges:

  • Safe removal of notifiable hazardous waste
  • Removal of contaminated waste to underground tanks
  • Close proximity to live cables
  • Party Wall negotiations, which included the appointment of a structural engineer and careful demolition works due to differing levels
  • Careful hand demolition to northern wall to ensure protection of neighbouring owner’s buildings

Achievements

  • Working close to private residencies without disruption or damage to property
  • Protection of live gas mains during demolition
  • Works completed on time and to budget